ERP Re-Implementation for a Multinational Manufacturer

A multinational manufacturer removed every core code customization from its IFS ERP and moved from IFS Apps 8 to Apps 10. The business now runs on standard IFS functionality and saves $200K a year in operating expenses.

Client
Multinational manufacturer
System
IFS ERP, live since 2016
Mandate
Standard IFS Apps 10 in one year, within budget
Mantrax role
Independent project lead, from partner selection through delivery

Four years in, the ERP was holding the business back

The client went live on IFS in 2016 with a heavily customized build. By 2020 the customizations cost more than they returned.

Half the system sat unused

50%

The business used about 50% of the IFS functionality it had purchased.

Half the customizations sat unused too

~50%

Only about 50% of the customizations built in 2016 were still in use.

  • Custom code caused downtime

    Outages traced back to changes made to IFS core code.

  • The upgrade path was closed

    The client was still on the version installed in 2016. Heavy customization blocked every new IFS release.

  • The business had lost confidence

    Teams resisted any new initiative that touched IFS.

The mandate: back to standard IFS in one year

The client chose to re-implement, not patch. The goal was to retire the custom code and run the business on standard IFS.

  1. 2016Go-live on IFS with heavy customization
  2. 2020Still on the 2016 version, with 50+ core code customizations
  3. Re-implementationOne-year mandate to move from Apps 8 to Apps 10
  4. TodayStandard IFS Apps 10, no core code customizations

What the client asked for

  • Eliminate 50+ core code customizations and move the business to standard IFS functionality.
  • Move the functionality in use from IFS Apps 8 to IFS Apps 10 within one year.
  • Stay within budget.

What Mantrax committed to

  • Protect day-to-day operations. The project could not tax the people running the business.
  • Let the business decide. The client's business team led every process decision. The project team presented the standard IFS options.
  • Make the project a good experience. After 2016, the project team and stakeholders needed a reason to trust the system again.

What Mantrax did

Mantrax ran the program as the client's independent lead, from partner selection through delivery.

  1. Selected the IFS partner

    Mantrax ran a structured selection: RFQ, vendor interviews, customer reference calls, and pilot projects with the shortlisted firms. The client chose its partner on demonstrated work, not a proposal.

  2. Structured the gap analysis

    Mantrax worked with the IFS partner and the client's subject matter experts to map the current system against standard Apps 10 functionality. Each gap was sorted into technical, functional, business process, or change management work, so the full effort was visible before the build started.

  3. Built the internal team

    Mantrax assessed the IFS skills and capacity the client had against what it would need. It then ran recruitment and onboarding to fill the gaps before re-implementation began.

  4. Managed the project day to day

    Mantrax provided hands-on project management, coached team members, and managed risk actively to hold the timeline.

  5. Managed every external vendor

    Mantrax aligned all vendors on the project objectives, set weekly work plans, and controlled the overall budget.

Results

The client now runs on standard IFS Apps 10 with no core code customizations.

  • 100% of core code customizations eliminated The source of the downtime is gone, and new IFS releases are usable again.
  • 100% of project scope delivered Every function the business relied on in Apps 8 moved to Apps 10.
  • 50% reduction in project resource allocation In line with the commitment to protect daily operations.
  • $200K annual savings in operating expenses A recurring saving, every year after go-live.
BeforeAfter
IFS versionApps 8, installed 2016Apps 10
Core code customizations50+None
New IFS releasesBlocked by customizationsUsable
How the business runsOn a customized buildOn standard IFS functionality

What made the difference

Four choices separated this project from the 2016 implementation.

  • The business owned the process decisions

    The project team showed how standard IFS could handle each process. The business chose. That is how a team that resisted IFS came to accept standard functionality.

  • The partner was tested before it was hired

    Pilot projects with shortlisted vendors showed how each firm worked before the client committed.

  • The internal team was built first

    The client filled its IFS skill and capacity gaps before the re-implementation, not during it.

  • One party held the vendors, the work plan and the budget

    Mantrax sat on the client's side of the table and managed all three together.

Is your ERP in the same position?

If your system is years behind the current release and customizations are the reason, the path back to standard is known. A discovery call covers where your customizations sit, what standard functionality now replaces, and what a re-implementation would take.